Published: 23 September 2026

Estates Strategy - 24 September 2026

Report Summary

This report provides members of the Scottish Police Authority with an overview of the Police Scotland Estate Strategy 2026 Refresh to members for review and approval. The refresh re-establishes the strategic framework for estates transformation, ensuring alignment with the Police Scotland 2030 Vision and responding to significant changes in the external environment, operational requirements, and financial context since publication of the 2019 Estate Strategy.

To access the full document please open the PDF document above.

To view as accessible content please use the sections below. (Note that tables and some appendixes are not available as accessible content). 

Meeting

The publication discussed was referenced in the meeting below

Green icons showing 7 inter-connected circles.

Meeting of the Scottish Police Authority - 24 September 2026

Date : 24 September 2026

Location : Clayton Hotel, 298 Clyde Street, Glasgow, G1 4NP


Report detail

This report accompanies the Police Scotland Estate Strategy 2026 Refresh (attached at Appendix A), which sets out the full detail of the proposed strategic direction, supporting analysis, and implementation framework.

This section provides a high-level summary of the key issues, rationale for change, and intended outcomes to support Board consideration and decision-making.
The Estate Strategy Refresh has been developed in response to significant changes since the publication of the 2019 strategy, including:
• The introduction of the Police Scotland 2030 Vision and associated business plans
• Shifting operational requirements and evolving policing models
• Increased financial pressures and constraints on public sector capital funding
• Changes in workforce expectations, including hybrid working and wellbeing requirements
• New national policy drivers, particularly around Net Zero, public estate collaboration, and public service reform

Whilst some progress has been made since 2019, the current estate remains ageing, inefficient, and not aligned to modern policing requirements, and is increasingly acting as a constraint on service delivery.

Current Estate Position
The analysis set out in Appendix A highlights that the existing estate:
• Is overly large, diverse and ageing, with a substantial proportion of buildings over 50 years old
• Has a significant maintenance backlog (c.£250m) requiring investment simply to maintain buildings
• Is expensive to operate, with costs forecast to exceed £80m annually
• Does not adequately support digital policing, collaboration, or workforce wellbeing
This position is financially unsustainable and limits the organisation’s ability to deliver the ambitions set out in the 2030 Vision.

Further detail

Case for Change
Appendix A sets out a clear and compelling case for change, based on the need to:
• Align the estate with modern and emerging operating models
• Address affordability and efficiency challenges
• Improve the quality and condition of buildings
• Support workforce wellbeing, recruitment and retention
• Enable a digitally enabled Police Scotland
• Deliver environmental sustainability and Net Zero ambitions Without transformation, there is a risk that the estate will continue to:
• Drive increasing operating and maintenance costs
• Require growing levels of “comfort spend”
• Inhibit operational effectiveness and service delivery

Strategic Direction
The Estate Strategy Refresh establishes a clear vision for a future estate that is:
• Effective, sustainable, accessible and inclusive
• Fit for modern and digitally enabled policing
• Supportive of workforce wellbeing
• Efficient, affordable and environmentally sustainable

To achieve this, the strategy centres on a number of key principles:
1. Rationalisation and Modernisation
• Reduction of the overall estate footprint
• Disposal of underutilised and inefficient properties
• Investment in a smaller number of modern, fit-for-purpose facilities
2. Hub and Spoke Model
• Creation of deployment hubs supported by community-based policing points
• Improved visibility and accessibility within communities
• Better alignment to operational policing models
3. Digitally Enabled Estate
• Infrastructure to support mobile and hybrid working
• Improved handling of digital evidence and operational data
• Alignment with the Police Scotland Digital Strategy
4. Co-location and Partnership Working
• Increased sharing of estate with public sector partners
• Delivery of more integrated and collaborative services
• Improved value for money from the public estate.

Benefits and Outcomes
As detailed in Appendix A, delivery of the Estate Strategy will provide wide-ranging benefits across a number of areas:
• Operational effectiveness: improved police visibility, responsiveness and service delivery
• Workforce outcomes: better working environments, improved wellbeing, and stronger recruitment and retention
• Financial sustainability: reduced operating costs and more effective capital investment
• Public value: enhanced community outcomes and improved use of public assets
• Environmental performance: reduced carbon footprint and improved energy efficiency.

Implementation Approach
The Estate Strategy Refresh does not represent a standalone plan but will be delivered through the existing Estate Master planning framework, as detailed in Appendix A.
Key features of the delivery approach include:
• A phased implementation model to manage complexity and resource constraints
• Prioritisation of high-risk and high-opportunity areas (notably Glasgow and Tayside)
• Development of robust business cases using the five-case model
• Strong governance through established Police Scotland and SPA structures

The Estate Strategy Refresh (Appendix A) provides a clear and necessary framework for transforming the Police Scotland estate into a modern, efficient and sustainable asset.

The strategy recognises that the current estate is no longer fit for purpose and that fundamental change is required to support the 2030 Vision, deliver improved services to the public, and ensure long-term financial sustainability.

Endorsement of this strategy will enable progression to the next stage of governance and delivery through the Estate Master planning programme.

 


Related Publications

The documents below are related by Topic and are the most recently published

Green icon showing weighing scales.

BRIEFING PAPER - Disposals Update including Project Falcon - 17 February 2026

Published: 12 February 2026

Estate

Green icon showing weighing scales.

Estates Consultation & Pre-Disposal Process - 16 December 2025

Published: 12 December 2025

Estate

Green icon with 2 arrows moving in different horizontal directions.

FOI 2025/26-060 - Report to Resources Committee regarding community asset transfer of Portobello Police Station – August 2025

Published: 19 September 2025

Estate

Green icons showing 7 inter-connected circles.

Estates Plan - 28 November 2024

Published: 27 November 2024

Estate